To build the Hejrat Park,
To build the Hejrat Park, the area was first identified and surveyed by the company's surveying team, and I and our surveying team did the surveying operation by using surveying instruments such as leveling instrument, Total Station, and Theodolite and so on to get the first surface of work.
The stations were determined according to the accuracy of harvesting and the ability to see the terrain on the ground and the croquis of the area was determined. I and the surveying team established the configuration of the ground and we created planimetric and topographic maps of the area.
After the ground operation, the company's cartographer emptied the surveying observation of the cameras on the computer (by the software ...) and after checking the status of the points with a croquis, we connected the points according to their number, We drew the relevant symbols in the desired layers this will speed up the ground operations on the next day.
After drawing the area, we went to the area to make sure the ready map and improve its quality, and we directly compared the map with the complications of the area in terms of incompatibility, changes or displacements.
Following the preparation of the plan, the relevant technical and executive plans were prepared, and after performing control calculations and determining the volume of operations and estimating the project costs, we proceeded
After the corners and axes and sides of the design on the ground were determined, We implemented the corners and axes and sides of the design by taping and surveying instruments and specified them with coloring stakes.
In order to control the operation of implementing the executive map, after staking out the corners and determining the axes, we proceeded before coloring stakes. We re-measured the sides and angles to make sure they were correct.
The points of the plan were extracted from the designed map and then these coordinates were transferred to the total station.
To perform table mapping in the area, we first obtained the desired cedar height according to the slopes provided in the map and the relevant calculations, and after determining the height difference compared to BM, we obtained the level hose.
According to the executive maps, the implementation operation will be carried out. I and the surveying team used the existing XYZ surveying instruments to implement the corners and axes, and the location of ponds, fountains, benches, recycle bins, cycling line, garden sides and we determined and after the last control of the operation by several surveyors, the project was delivered to the employer.